A) Risk reduction
B) Risk mitigation
C) Risk evaluation
Correct Answer
verified
Multiple Choice
A) Ineffective, unnecessary or inappropriate inspection activities may be eliminated
B) Effective, necessary or appropriate inspection activities may be eliminated
C) On-line or non-invasive inspection methods may be substituted for invasive methods that require equipment shutdown
D) More effective infrequent inspections may be substituted for less effective frequent inspections
Correct Answer
verified
Multiple Choice
A) Cost
B) Release
C) Volume of fluid
D) Toxic concentration
Correct Answer
verified
Multiple Choice
A) Conducive to certain cracking mechanisms
B) Unfavorable to certain cracking mechanisms
C) Unbeneficial to certain cracking mechanisms
Correct Answer
verified
Multiple Choice
A) Deterioration mechanism
B) Effectiveness of inspection program
C) Consequence detailed
D) A&B
Correct Answer
verified
Multiple Choice
A) Stress corrosion cracking
B) Hydrogen induced cracking
C) Thinning
D) All of the above
E) Both A and B
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Risk reduction
B) Risk evaluation
C) Risk mitigation
D) Risk control
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) Risk
B) Failure
C) Loss
D) Reduction
Correct Answer
verified
Multiple Choice
A) General industry, company or manufacturer failure data used
B) Process hazard analysis failure data may be used
C) Process and toxic concentration analysis may be used
Correct Answer
verified
Multiple Choice
A) Risk
B) Risk analysis
C) Hazard analysis
Correct Answer
verified
Multiple Choice
A) RBI
B) PHA
C) REM
D) HAZOP
Correct Answer
verified
Multiple Choice
A) Precise numeric value
B) Form of risk matrix
C) Form of event tree and fault tree
Correct Answer
verified
Multiple Choice
A) By equipment complexity
B) Type of deterioration mechanism, process and metallurgical variations
C) Inaccessibility for inspection, limitations of inspection and test methods
D) Lack of coverage of an area subject to deterioration
E) None of the above
Correct Answer
verified
Multiple Choice
A) Expert judgment
B) Inspection engineer
C) Maintenance engineer
D) Operations personnel
Correct Answer
verified
Multiple Choice
A) Risk management
B) Risk evaluation
C) Risk control
Correct Answer
verified
Multiple Choice
A) Replacement or upgrade
B) Equipment redesign
C) Maintenance of strict controls on operating conditions
D) Risk management by monitoring the deterioration
Correct Answer
verified
Multiple Choice
A) Risk evaluation
B) Risk estimation
C) Risk identification
Correct Answer
verified
Multiple Choice
A) The volume of fluid released
B) Amount of surface area exposed due to toxic release
C) Physical area impacted by release
Correct Answer
verified
Showing 81 - 100 of 134